News

UETCL Says Nationwide Power Blackout Was Due To Technical Issues At Karuma Plant

UETCL Says Nationwide Power Blackout Was Due To Technical Issues At Karuma Plant

PHOTO: Karuma Hydro Power Plant (UETCL)

The Uganda Electricity Transmission Company Limited (UETCL) has revealed that the unplanned nation-wide power blackout that occured on Friday was due to technical issues involving defective transmission at the Karuma Hydro Power Plant.

The blackout happened on Friday morning lasting hours, according to UETCL.

"UETCL informs the general public that a national blackout has been registered this morning following a load rejection test at the Karuma Hydro Electric Plant," the parastatal announced on Friday afternoon.

The purpose of a load rejection test is to assess the gas turbine's stability and control system response when a sudden load change occurs.

The 600MW Karuma HPP is located on the Nile River in Kiryandongo District in mid-northern Uganda, 110km downstream of Lake Kyoga, and 270km from Kampala the Capital of Uganda.

Construction of Karuma Hydroelectric Station, the largest power-generating installation in the country started in 2013. The project has faced multiple delays and extra costs along the way, with the initial completion date veing shifted from 2013 to 2018. Construction costs have also risen, with the project initially estimated at USD 1.7 billion (approximately 6.323 trillion Uganda Shillings) to 8.183 trillion Uganda Shillings due to implementation challenges.

Karuma power project is expected to add on to Uganda's rich power supply capacity that comprises 183MW from Isimba Hydro Power Project in Kayunga, 83MW from Achwa Hydroelectric Power in Pader, and 3.5MW Nyagak Power Plant in Zombo District. This capacity is expected to hit the 2,000 MW mark on e the Karuma project is fully completed.

All this is part of Government's efforts to achieve universal access to electricity by Ugandans by 2030.

Osbert Mwesigye