The government of Uganda through National Water and Sewerage Cooperation (NWSC) is in the final stages of construction of q new water treatment plant in Katosi, Mukono district.
When completed the plant will serve a total of over 7.5 million dwellers across the region of Kampala, Wakiso and Mukono.
According to government, works on the plant are about 95% done and completion of the remaining 5% is currently going on.

The treatment plant which is expected to serve the aforementioned region until the year 2040 boasts of an output of 240million litres per day.
The project manager, Eng Denis Taremwa, said that works are on course with the first drop of water expected to reach the new Nsumba water reservoirs by the end of April 2021.
NWSC MD Dr. Eng Silver Mugisha said, while assessing the ongoing works, that water supply challenges in Kampala, Wakiso and Mukono districts will soon be history.

This follows 100% completion of the Katosi Water Treatment Plant civil works, commencement of system tests and final installations at the facility.
“We are happy with the progess made so far by the contractor and consultant,” Eng Mugisha said.
“We experienced logistical challenges in the delivery of some plant components. However, the good news is, the remaining 1.5kms of the pipe line was delivered and a km has already been laid, with 500m to go.” Mugisha added.
Engineer Alex Gasagara, the Director Engineering Services, said that the works on-going at the moment include the following:
• Raw water and treated water pumps all installed and connected to power grid
• Offshore pipeline (500m)is already laid on the lake bed.
• More than 8.0km out of 9.5km of the pumping main already laid and undergoing pressure testing.
•Testing and commisioning of different Plant electrical control units.
• Final finishes on the process and none-process buildings/structures are ongoing
•Land scaping and greening of the Plant currently ongoing” he shared
Modern techniques.
The Deputy Managing Director Technical Services Eng Johnson Amayo said that new methods of water purification and treatment shall be used in the new plant. A new technique called air floatation will replace sedimentation to deal with the increasing levels of algae in Lake Victoria.
“Upon completion, the Katosi plant will be the first and biggest plant in East and Central Africa using the AquaDAF and AquaZur technologies” he said.
The state of the art plant shall incorporate water recycling and sludge thickening to minimise plant losses and promote environmental conservation.
The scope of the water treatment project according to the technical team.
• A modern laboratory to enhance water quality monitoring and management
• A mechanical workshop
• A scada system that will be integrated with the existing NWSC installations
•A compact wastewater treatment plant
•A solidwaste handling and incineration facility
• A 500m offshore abstraction pipeline into Lake Victoria.
• A modern staff housing estate with modern amenities and recreation facilities