Members of Parliament on the Environment and Natural Resources Committee have demanded answers on how the money allocated to the Muvumbe mini hydropower plant in Maziba Sub County in Kabale district was used.

The MPs yesterday were shocked to learn that the 60-year-old power plant stopped working in 2007 and yet it has been receiving money in every budget in recent years.

The committee members found this out while touring the plant as part of their oversight work on government energy installations in the western part of Uganda.

“We have been sending money, and we want to know how it was being used,” charged Hon Emmanuel Otala, the committee chairman.

“We are going to follow up on this and we want to get answers on why no work was done.”

In response, Mr Daniel Oringa, the principal compliance Engineer at the Electricity Regulatory Authority (ERA) told the MPs that the money was being sent directly to the Uganda Electricity Generation Company Ltd and that they should be the ones to account for it.

The hydropower plant was built in 1963 and operated by the Uganda Electricity Board to boost power supply in Kabale and other parts of the Kigezi subregion.

The plant was generating 0.8 Megawatts of power. According to Mr Oringa, plans have been ongoing to revive the defunct plant.

“The site has undergone studies and we expect that in the near future, might undergo refurbishment or total development depending on which one is most feasible,” he said.

The plant’s original capacity was 0.8MW, but studies show that if developed it could go up to 4MW.